As manufacturers are reaping the benefits of Lean and Lean Six Sigma or other continuous improvement processes within their facilities the importance of eliminating waste still hold sway. So the question now facing these manufacturers is this:
Has the time come where Just-in-Time inventory levels need to be changed to Just-in-Case levels? With the present and at least near future volatility of the economy this may prove to be the case. The answer lies within each company’s own supply chain and decided upon based on each company’s individual requirements.
Inventory is considered one of the seven (7) wastes in a lean manufacturing environment. It is any material over and above what is required for use in the process. The JIT environment basically works much like this: a piece per process > one piece delivered > one piece processed > one piece shipped. Any and all inventory on hand after this process can be viewed as waste.
There is no such thing as the ideal situation and it’s quite impractical. Thus, inventory is carried within the facility. In practice just about every company carries inventory of some magnitude. And thus many issues ensue – excess storage requirements, carrying costs, increased material handling and obsolescence. The real concern should lie within the raw materials inventory levels as finished goods and sub-assemblies are in company’s control – based upon customer service levels and on-time delivery rates.
Over the past several months many small companies have shuttered their businesses. Much of this occurred when a primary supplier shutdown operations and damaged your delivery performance.
Under these circumstances perhaps it is time for the remaining small manufacturers to take a good hard look at their suppliers and ask the following questions:
- How well do you know your first, second and third tier suppliers?
- Are any of them at risk of closing their doors and catching you off guard?
- Have you looked at their financial health?
Maybe the time has come to get to know them better. Harks back to making your suppliers your business partners. The slightest change or disruption upstream can cause a major effect downstream. It might be a good idea to carry a few weeks inventory to protect the company until the risk potential with this supplier can be evaluated. Perhaps a visit to this third tier supplier would be in order to avoid higher future costs.
Start this process by reviewing some of the more vulnerable suppliers. For example: if you are in the automobile industry start by checking the health and stability of suppliers you share with the North American automakers.
In any industry, in order to implement JIC, and to determine how much and type of inventory need to carry these questions require honest answers:
- How difficult will it be to source replacement parts?
- How long does it take to get customer approval to move the tooling?
- How much testing is required if a new supplier is needed in an emergency?
- How long can you delay in shipping to your customers before it affects relations?
- How much space will be required to carry enough stock in case of emergency?
The answers to these questions will point the way to determining the on-hand inventory levels. In addition, with good strategy and procedures it should also help to determine which components are at the greatest risk.
Please keep in mind that JIC could be a temporary solution to a temporary problem. It is extremely expensive to carry JIC inventory for every part, so the decision needs to be made as to which parts are the most critical. Be aware, the carrying cost may increase exponentially, at least in the short run. Consider JIC an insurance policy but when the crisis is over re-think the policy and return to JIT and LEAN.
Bio:
Expertise in lean six sigma manufacturing systems, inventory systems and process improvements functions. Accomplished in use of optimization models to determine least cost facilities and drill down to workflow details in support of process and profit management. Oversaw all Inventory Collaborate effectively with business managers to resolve variances, refine forecasts and identify opportunities for improvement. While at Reckitt Benckiser, Linde Gas and Johnson & Johnson wore several hats including inventory manager, implementer and trainer of benchmarking and dashboard analytics, leader of cost optimization projects such as Lean and Lean Six Sigma, created and implemented cost and inventory metrics, collaborated across functional silos such as production, receiving, plant personnel and shipping to ensure inventory and cost systems integrity, wrote and implemented and trained staff on new Procedures to align with projects and continuous improvement leader.
Member of various accounting and operational trade associations such as; The Council of Supply Chain Management Professionals, The International Supply Chain Education Alliance and The Society of Cost Management. My interests outside of my work are mostly outdoor activities like hiking, camping, tennis, etc., with a slight lean to gourmet cooking.
Lean Six Sigma Certified White Belt
Lean Six Sigma Trained Green Belt
www.linkedin.com/in/stuartrosenberg1
www.StuLeanSixSigma.wordpress.com
Mobile # 917.952.6715
Home Office # 732.698.2817
Email: rosen-cost-acct@comcast.net